V,
Unit Rate Amount FC LC Unit Rate Amount FC LC
(US$) (US$) (US$) (US$) (US$) (US$) (US$) (US$)
1 Tower ton 153 2,100 321,300 321,300 0 ton 201 2,100 422,100 422,100 0
2 Conductor km 30 6,200 186,000 186,000 0 km 60 6,200 372,000 372,000 0
3 OPGW 60mm2 km 0 6,100 0 0 0 km 0 6,100 0 0 0
4 OH G.W. km 10 1,550 15,500 15,500 0 km 10 1,550 15,500 15,500 0
5 Suspension Insulator String set 81 400 32,400 32,400 0 set 162 400 64,800 64,800 0
6 Tension Insulator String set 18 600 10,800 10,800 0 set 36 600 21,600 21,600 0
7 Accessories lot 1 6% 33,960 33,960 0 lot 1 6% 53,760 53,760 0
Subtotal 599,960 599,960 0 949,760 949,760 0
1 Survey & S. Investigation km 10 2,000 20,000 8,000 12,000 km 10 2,000 20,000 8,000 12,000
2 Access Construction km 20 1,000 20,000 6,000 14,000 km 20 1,000 20,000 6,000 14,000
3 Land Clearing km 10 1,000 10,000 2,000 8,000 km 10 1,000 10,000 2,000 8,000
4 Foundation (Volume of Concrete) m
3210 750 157,500 31,500 126,000 m
3227 750 170,250 34,050 136,200
5 Tower Erection ton 153 240 36,720 11,016 25,704 ton 201 240 48,240 14,472 33,768
6 Stringing km 10 3,000 30,000 9,000 21,000 km 20 3,000 60,000 18,000 42,000
7 Inland Transportion CIF*12% 71,995 0 71,995 CIF*12% 113,971 0 113,971
8 Miscellaneous lot 1 5% 17,311 3,376 13,935 lot 1 5% 22,123 4,126 17,997
9 General Expenses lot 1 10% 36,353 7,089 29,263 lot 1 10% 46,458 8,665 37,794
Subtotal 399,879 77,981 321,898 511,043 95,313 415,730
Total 999,839 677,941 321,898 1,460,803 1,045,073 415,730
Estimated Condition ; Aluminum base LME 1550US$/ton, Exchange Rate ; 100Yen/US$, 3.0Yen/THB
表10.3-2(4) Assumpted Estimation for TL Construction Cost Vol.4
"Voltage; 115kV, Conductor; Drake, Single, Soil Condition; Normal, Passing Area; Plain "
Items Remarks
Unit Q'ty Unit Q'ty
Laos ( Lao People's Democratic Republic ) for
Assumption:
(1) Length: 10km
(2) Ratio of Tenssion Towers for All Towers: 90% of Suspenssion Towers (27units), 10% of Tenssion Towers (3units) (3) Average Span: 350m
(4) Foundation Type: 100% of Pad Type Foundations (5) Soil Conditions: Normal
115kV, 1cct, (10km) Condutcor : Drake, Single
115kV, 2cct, (10km) Condutcor : Drake, Single
COSTOF LABOUR, INLAND TRANSPORTATION AND EXPENSES
Cat e gor y No.
COST, INSURANCE AND FREIGHT
Unit Rate Amount FC LC Unit Rate Amount FC LC
(US$) (US$) (US$) (US$) (US$) (US$) (US$) (US$)
1 Tower ton 251 2,100 527,100 527,100 0 ton 361 2,100 758,100 758,100 0
2 Conductor km 60 8,400 504,000 504,000 0 km 120 8,400 1,008,000 1,008,000 0
3 OPGW 60mm2 km 10 6,100 61,000 61,000 0 km 10 6,100 61,000 61,000 0
4 OH G.W. km 10 1,550 15,500 15,500 0 km 10 1,550 15,500 15,500 0
5 Suspension Insulator String set 162 600 97,200 97,200 0 set 162 800 129,600 129,600 0
6 Tension Insulator String set 36 800 28,800 28,800 0 set 36 1,000 36,000 36,000 0
7 Accessories lot 1 6% 70,356 70,356 0 lot 1 6% 116,832 116,832 0
Subtotal 1,303,956 1,303,956 0 2,125,032 2,125,032 0
1 Survey & S. Investigation km 10 2,000 20,000 8,000 12,000 km 10 2,000 20,000 8,000 12,000
2 Access Construction km 20 1,000 20,000 6,000 14,000 km 20 1,000 20,000 6,000 14,000
3 Land Clearing km 10 1,000 10,000 2,000 8,000 km 10 1,000 10,000 2,000 8,000
4 Foundation (Volume of Concrete) m
3372 750 279,000 55,800 223,200 m
3429 750 321,750 64,350 257,400
5 Tower Erection ton 251 240 60,240 18,072 42,168 ton 361 240 86,640 25,992 60,648
6 Stringing km 20 3,000 60,000 18,000 42,000 km 30 3,000 90,000 27,000 63,000
7 Inland Transportion CIF*12% 156,475 0 156,475 CIF*12% 255,004 0 255,004
8 Miscellaneous lot 1 5% 30,286 5,394 24,892 lot 1 5% 40,170 6,667 33,503
9 General Expenses lot 1 10% 63,600 11,327 52,273 lot 1 10% 84,356 14,001 70,355
Subtotal 699,601 124,592 575,008 927,920 154,010 773,910
Total 2,003,557 1,428,548 575,008 3,052,952 2,279,042 773,910
Estimated Condition ; Aluminum base LME 1550US$/ton, Exchange Rate ; 100Yen/US$, 3.0Yen/THB 230kV, 2cct, (10km)
Condutcor : Bittern, Single
230kV, 2cct, (10km) Condutcor : Bittern, Double
COSTOF LABOUR, INLAND TRANSPORTATION AND EXPENSES
Cat e go ry No.
COST, INSURANCE AND FREIGHT
表10.3-2(5) Assumpted Estimation for TL Construction Cost Vol.5
"Voltage; 115kV, Conductor; Drake, Single, Soil Condition; Normal, Passing Area; Plain "
Items Remarks
Unit Q'ty Unit Q'ty
Laos ( Lao People's Democratic Republic ) for
Assumption:
(1) Length: 10km
(2) Ratio of Tenssion Towers for All Towers: 90% of Suspenssion Towers (27units), 10% of Tenssion Towers (3units) (3) Average Span: 350m
(4) Foundation Type: 100% of Pad Type Foundations
(5) Soil Conditions: Normal
Unit Rate Amount FC LC Unit Rate Amount FC LC
(US$) (US$) (US$) (US$) (US$) (US$) (US$) (US$)
1 Tower ton 128 2,100 268,800 268,800 0 ton 156 2,100 327,600 327,600 0
2 Conductor km 30 4,900 147,000 147,000 0 km 60 4,900 294,000 294,000 0
3 OPGW 60mm2 km 0 6,100 0 0 0 km 0 6,100 0 0 0
4 OH G.W. km 10 1,550 15,500 15,500 0 km 10 1,550 15,500 15,500 0
5 Suspension Insulator String set 63 400 25,200 25,200 0 set 126 400 50,400 50,400 0
6 Tension Insulator String set 54 600 32,400 32,400 0 set 108 600 64,800 64,800 0
7 Accessories lot 1 6% 29,334 29,334 0 lot 1 6% 45,138 45,138 0
Subtotal 518,234 518,234 0 797,438 797,438 0
1 Survey & S. Investigation km 10 2,000 20,000 8,000 12,000 km 10 2,000 20,000 8,000 12,000
2 Access Construction km 20 1,500 30,000 9,000 21,000 km 20 1,500 30,000 9,000 21,000
3 Land Clearing km 10 1,300 13,000 2,600 10,400 km 10 1,300 13,000 2,600 10,400
4 Foundation (Volume of Concrete) m
3147 1,100 161,700 32,340 129,360 m
3262 1,100 288,200 57,640 230,560
5 Tower Erection ton 128 360 46,080 13,824 32,256 ton 156 360 56,160 16,848 39,312
6 Stringing km 10 4,500 45,000 13,500 31,500 km 20 4,500 90,000 27,000 63,000
7 Inland Transportion CIF*12% 62,188 0 62,188 CIF*12% 95,693 0 95,693
8 Miscellaneous lot 1 5% 18,898 3,963 14,935 lot 1 5% 29,653 6,054 23,598
9 General Expenses lot 1 10% 39,687 8,323 31,364 lot 1 10% 62,271 12,714 49,556
Subtotal 436,553 91,550 345,003 684,976 139,857 545,119
Total 954,787 609,784 345,003 1,482,414 937,295 545,119
Estimated Condition ; Aluminum base LME 1550US$/ton, Exchange Rate ; 100Yen/US$, 3.0Yen/THB
表10.3-2(6) Assumpted Estimation for TL Construction Cost Vol.6
"Voltage; 115kV, Conductor; Hawk, Single, Soil Condition; Normal, Passing Area; Mountain "
Items Remarks
Unit Q'ty Unit Q'ty
Laos ( Lao People's Democratic Republic ) for
Assumption:
(1) Length: 10km
(2) Ratio of Tenssion Towers for All Towers: 70% of Suspenssion Towers (21units), 30% of Tenssion Towers (9units) (3) Average Span: 350m
(4) Foundation Type: 100% of Pad Type Foundations (5) Soil Conditions: Normal
115kV, 2cct, (10km) Condutcor : Hawk, Single 115kV, 1cct, (10km)
Condutcor : Hawk, Single
COSTOF LABOUR, INLAND TRANSPORTATION AND EXPENSES
Cat e gor y No.
COST, INSURANCE AND FREIGHT
Unit Rate Amount FC LC Unit Rate Amount FC LC
(US$) (US$) (US$) (US$) (US$) (US$) (US$) (US$)
1 Tower ton 159 2,100 333,900 333,900 0 ton 205 2,100 430,500 430,500 0
2 Conductor km 30 6,200 186,000 186,000 0 km 60 6,200 372,000 372,000 0
3 OPGW 60mm2 km 0 6,100 0 0 0 km 0 6,100 0 0 0
4 OH G.W. km 10 1,550 15,500 15,500 0 km 10 1,550 15,500 15,500 0
5 Suspension Insulator String set 63 400 25,200 25,200 0 set 126 400 50,400 50,400 0
6 Tension Insulator String set 54 600 32,400 32,400 0 set 108 600 64,800 64,800 0
7 Accessories lot 1 6% 35,580 35,580 0 lot 1 6% 55,992 55,992 0
Subtotal 628,580 628,580 0 989,192 989,192 0
1 Survey & S. Investigation km 10 2,000 20,000 8,000 12,000 km 10 2,000 20,000 8,000 12,000
2 Access Construction km 20 1,500 30,000 9,000 21,000 km 20 1,500 30,000 9,000 21,000
3 Land Clearing km 10 1,300 13,000 2,600 10,400 km 10 1,300 13,000 2,600 10,400
4 Foundation (Volume of Concrete) m
3210 1,100 231,000 46,200 184,800 m
3262 1,100 288,200 57,640 230,560
5 Tower Erection ton 159 360 57,240 17,172 40,068 ton 205 360 73,800 22,140 51,660
6 Stringing km 10 4,500 45,000 13,500 31,500 km 20 4,500 90,000 27,000 63,000
7 Inland Transportion CIF*12% 75,430 0 75,430 CIF*12% 118,703 0 118,703
8 Miscellaneous lot 1 5% 23,583 4,824 18,760 lot 1 5% 31,685 6,319 25,366
9 General Expenses lot 1 10% 49,525 10,130 39,396 lot 1 10% 66,539 13,270 53,269
Subtotal 544,778 111,425 433,353 731,927 145,969 585,958
Total 1,173,358 740,005 433,353 1,721,119 1,135,161 585,958
Estimated Condition ; Aluminum base LME 1550US$/ton, Exchange Rate ; 100Yen/US$, 3.0Yen/THB 115kV, 1cct, (10km)
Condutcor : Drake, Single
115kV, 2cct, (10km) Condutcor : Drake, Single
COSTOF LABOUR, INLAND TRANSPORTATION AND EXPENSES
Cat e gor y No.
COST, INSURANCE AND FREIGHT
表10.3-2(7) Assumpted Estimation for TL Construction Cost Vol.7
"Voltage; 115kV, Conductor; Drake, Single, Soil Condition; Normal, Passing Area; Mountain "
Items Remarks
Unit Q'ty Unit Q'ty
Laos ( Lao People's Democratic Republic ) for
Assumption:
(1) Length: 10km
(2) Ratio of Tenssion Towers for All Towers: 70% of Suspenssion Towers (21units), 30% of Tenssion Towers (9units) (3) Average Span: 350m
(4) Foundation Type: 100% of Pad Type Foundations
(5) Soil Conditions: Normal
Unit Rate Amount FC LC Unit Rate Amount FC LC
(US$) (US$) (US$) (US$) (US$) (US$) (US$) (US$)
1 Tower ton 259 2,100 543,900 543,900 0 ton 369 2,100 774,900 774,900 0
2 Conductor km 60 8,400 504,000 504,000 0 km 120 8,400 1,008,000 1,008,000 0
3 OPGW 60mm2 km 10 6,100 61,000 61,000 0 km 10 6,100 61,000 61,000 0
4 OH G.W. km 10 1,550 15,500 15,500 0 km 10 1,550 15,500 15,500 0
5 Suspension Insulator String set 126 600 75,600 75,600 0 set 126 800 100,800 100,800 0
6 Tension Insulator String set 108 800 86,400 86,400 0 set 108 1,000 108,000 108,000 0
7 Accessories lot 1 6% 73,524 73,524 0 lot 1 6% 120,432 120,432 0
Subtotal 1,359,924 1,359,924 0 2,188,632 2,188,632 0
1 Survey & S. Investigation km 10 2,000 20,000 8,000 12,000 km 10 2,000 20,000 8,000 12,000
2 Access Construction km 20 1,500 30,000 9,000 21,000 km 20 1,500 30,000 9,000 21,000
3 Land Clearing km 10 1,300 13,000 2,600 10,400 km 10 1,300 13,000 2,600 10,400
4 Foundation (Volume of Concrete) m
3372 1,100 409,200 81,840 327,360 m
3543 1,100 597,300 119,460 477,840
5 Tower Erection ton 259 360 93,240 27,972 65,268 ton 369 360 132,840 39,852 92,988
6 Stringing km 20 4,500 90,000 27,000 63,000 km 30 4,500 135,000 40,500 94,500
7 Inland Transportion CIF*12% 163,191 0 163,191 CIF*12% 262,636 0 262,636
8 Miscellaneous lot 1 5% 40,932 7,821 33,111 lot 1 5% 59,539 10,971 48,568
9 General Expenses lot 1 10% 85,956 16,423 69,533 lot 1 10% 125,031 23,038 101,993
Subtotal 945,519 180,656 764,863 1,375,346 253,421 1,121,925
Total 2,305,443 1,540,580 764,863 3,563,978 2,442,053 1,121,925
Estimated Condition ; Aluminum base LME 1550US$/ton, Exchange Rate ; 100Yen/US$, 3.0Yen/THB
表10.3-2(8) Assumpted Estimation for TL Construction Cost Vol.8
"Voltage; 115kV, Conductor; Drake, Single, Soil Condition; Normal, Passing Area; Plain "
Items Remarks
Unit Q'ty Unit Q'ty
Laos ( Lao People's Democratic Republic ) for
Assumption:
(1) Length: 10km
(2) Ratio of Tenssion Towers for All Towers: 70% of Suspenssion Towers (21units), 30% of Tenssion Towers (9units) (3) Average Span: 350m
(4) Foundation Type: 100% of Pad Type Foundations (5) Soil Conditions: Normal
230kV, 2cct, (10km) Condutcor : Bittern, Single
230kV, 2cct, (10km) Condutcor : Bittern, Double
COSTOF LABOUR, INLAND TRANSPORTATION AND EXPENSES
Ca te go ry No.
COST, INSURANCE AND FREIGHT
表10.3-5 2010-2030年の送電線開発計画
(unit: 1,000USD) origination terminal voltage (kV) year No. of cct conductor type length (km) area UXO pollution total 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 Northern
Boun Neua Namo 115 2012 2 ACSR240 96.0 Mountain N/A 14,231 FC 8,998.0 990 6,748 1,260
2012 LC 5,233.2 628 3,035 1,570
Boun Neua Cu Mining 115 2012 1 ACSR240 65.0 Mountain N/A 6,206 FC 3,963.6 436 2,973 555
2012 LC 2,242.5 269 1,301 673
Boun Neua Cu Mining 115 2014 1 ACSR240 65.0 Mountain N/A 6,206 FC 3,963.6 436 2,973 555
2014 LC 2,242.5 269 1,301 673
Luang Namtha Cu Mining 115 2010 1 ACSR240 60.0 Mountain N/A 5,729 FC 3,658.7 3,659
2010 LC 2,070.0 2,070
Namo Cu Mining 115 2012 1 ACSR240 15.0 Mountain N/A 1,432 FC 914.7 101 686 128
2012 LC 517.5 62 300 155
Nam Ou 6 Boun Neua 115 2017 2 ACSR240 40.0 Mountain N/A 5,930 FC 3,749.2 412 2,812 525
2017 LC 2,180.5 262 1,265 654
Luang Namtha Nam Thoung 115 2012 2 ACSR240 91.0 Mountain N/A 13,490 FC 8,529.3 938 6,397 1,194
2012 LC 4,960.6 595 2,877 1,488
Luang Namtha Namo 115 2015 1* ACSR240 42.7 Mountain N/A 1,276 FC 992.6 993
2015 LC 283.7 284
Nam Thoung Houayxai 115 2012 1 ACSR240 40.0 Mountain N/A 3,819 FC 2,439.1 268 1,829 341
2012 LC 1,380.0 166 800 414
Nam Thoung Nam Tha 1 115 2012 2 ACSR240 42.0 Mountain N/A 6,226 FC 3,936.6 433 2,952 551
2012 LC 2,289.5 275 1,328 687
Nam Tha 1 Hongsa 115 2015 2 ACSR410 93.0 Mountain N/A 16,006 FC 10,557.0 1,161 7,918 1,478
2015 LC 5,449.4 654 3,161 1,635
Nam Beng Switching Station 115 2020 1 ACSR240 15.0 Mountain N/A 1,432 FC 914.7 101 686 128
2020 LC 517.5 62 300 155
Oudomxai Namo 115 2013 1* ACSR240 41.0 Mountain N/A 1,226 FC 953.1 953
2013 LC 272.4 272
Luangprabang 2 Oudomxai 115 2013 1* ACSR240 51.8 Mountain N/A 1,548 FC 1,204.2 1,204
2013 LC 344.2 344
Oudomxai THLC Mining 115 2012 1 ACSR240 20.0 Mountain N/A 1,910 FC 1,219.6 134 915 171
2012 LC 690.0 83 400 207
Luangprabang 2 Cement Factory 115 2010 1 ACSR240 25.0 Mountain Light 2,387 FC 1,524.5 1,524
2010 LC 862.5 863
2010 300 FC 99.0 99
2010 LC 201.0 201
Luangprabang 2 United 115 2010 1 ACSR240 15.0 Mountain Light 1,432 FC 914.7 915
2010 LC 517.5 518
2010 180 FC 59.4 59
2010 LC 120.6 121
Nam Nga Luangprabang 2 115 2020 1 ACSR240 15.0 Mountain N/A 1,432 FC 914.7 101 686 128
2020 LC 517.5 62 300 155
Luangprabang 1 Luangprabang 2 115 2013 1* ACSR240 86.9 Mountain Light 2,598 FC 2,020.2 222 1,515 283
2013 LC 577.4 69 335 173
2013 1,043 FC 344.1 310 34
2013 LC 698.7 629 70
Luangprabang 1 Luangprabang 3 115 2013 2 ACSR240 15.0 Mountain N/A 2,224 FC 1,405.9 155 1,054 197
2013 LC 817.7 98 474 245
Hongsa Luangprabang 3 115 2015 2 ACSR410 100.0 Mountain N/A 17,211 FC 11,351.6 1,249 8,514 1,589
2015 LC 5,859.6 703 3,399 1,758
Mekong Luangprabang Luangprabang 3 115 2016 2 ACSR410 40.0 Mountain Light 6,884 FC 4,540.6 499 3,405 636
2016 LC 2,343.8 281 1,359 703
2016 480 FC 158.4 143 16
2016 LC 321.6 289 32
Nam Ma 1 Nam Ma 2 115 2016 1 ACSR240 20.0 Mountain Light 1,910 FC 1,219.6 134 915 171
2016 LC 690.0 83 400 207
2016 240 FC 79.2 71 8
2016 LC 160.8 145 16
Nam Ma 2 Nam Ma 3 115 2016 1 ACSR240 20.0 Mountain Light 1,910 FC 1,219.6 134 915 171
2016 LC 690.0 83 400 207
2016 240 FC 79.2 71 8
2016 LC 160.8 145 16
Nam Ma 1 Xam Neua 115 2016 2 ACSR240 40.0 Mountain Heavy 5,930 FC 3,749.2 412 2,812 525
2016 LC 2,180.5 262 1,265 654
2016 680 FC 224.4 202 22
2016 LC 455.6 410 46
Xam Neua Muong Kham 115 2011 2 ACSR240 146.0 Mountain Heavy 21,643 FC 13,684.4 11,769 1,916
2011 LC 7,958.8 5,571 2,388
表10.3-5 2010-2030年の送電線開発計画
(unit: 1,000USD) origination terminal voltage (kV) year No. of cct conductor type length (km) area UXO pollution total 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
2011 2,482 FC 819.1 737 82
2011 LC 1,662.9 1,497 166
Nam Khan 2 Nam Khan 3 115 2018 1 ACSR240 45.0 Mountain Light 4,297 FC 2,744.0 302 2,058 384
2018 LC 1,552.5 186 900 466
2018 540 FC 178.2 160 18
2018 LC 361.8 326 36
Luangprabang 3 Nam Khan 2 230 2018 2 ACSR610 36.0 Mountain N/A 8,300 FC 5,546.1 610 4,160 776
2018 LC 2,753.5 330 1,597 826
Nam Mo 1 Muong Kham 115 2020 1 ACSR240 45.0 Mountain Heavy 4,297 FC 2,744.0 302 2,058 384
2020 LC 1,552.5 186 900 466
2020 765 FC 252.5 227 25
2020 LC 512.6 461 51
Muong Kham Fe Mining 115 2011 1 ACSR240 40.0 Mountain Heavy 3,819 FC 2,439.1 2,098 341
2011 LC 1,380.0 966 414
2011 680 FC 224.4 202 22
2011 LC 455.6 410 46
Phonsavan Muong Kham 115 2011 2 ACSR410 56.2 Mountain Heavy 9,673 FC 6,379.6 5,486 893
2011 LC 3,293.1 2,305 988
2011 955 FC 315.3 284 32
2011 LC 640.1 576 64
Phonsavan Fe Mining 115 2012 1 ACSR240 20.0 Mountain Heavy 1,910 FC 1,219.6 134 915 171
2012 LC 690.0 83 400 207
2012 340 FC 112.2 101 11
2012 LC 227.8 205 23
Xayabury Paklay 115 2014 2 ACSR240 134.0 Plain N/A 16,392 FC 11,318.0 1,245 8,489 1,585
2014 LC 5,073.8 609 2,943 1,522
Paklay Cu Mining 115 2014 1 ACSR240 25.0 Mountain N/A 2,387 FC 1,524.5 168 1,143 213
2014 LC 862.5 104 500 259
Paklay Thali 115 2014 1 ACSR240 86.2 Plain N/A 6,963 FC 4,785.8 526 3,589 670
2014 LC 2,177.2 261 1,263 653
New Switching Station (TNam San 3 115 2016 1 ACSR240 28.0 Mountain Light 2,673 FC 1,707.4 188 1,281 239
2016 LC 966.0 116 560 290
2016 336 FC 110.9 100 11
2016 LC 225.1 203 23
Namo Cement Factory 115 2012 1 ACSR240 5.0 Mountain N/A 477 FC 304.9 34 229 43
2012 LC 172.5 21 100 52
TL Construction Northern Total
213,416FC
139,254.0028,885 26,942 9,349 21,470 20,865 13,800 5,466 6,743 1,664 3,430 640 0 0 0 0 0 0 0 0 0 0
LC
74,162.0014,454 14,398 7,474 8,498 10,544 7,923 3,842 3,151 1,602 1,500 776 0 0 0 0 0 0 0 0 0 0
UXO Removal Northern Total
9,262FC
3,055.001,482 446 11 34 587 0 225 0 245 0 25 0 0 0 0 0 0 0 0 0 0
LC
6,207.003,010 905 23 70 1,192 0 459 0 497 0 51 0 0 0 0 0 0 0 0 0 0
ドキュメント内
第 8 章最優先プロジェクトの 選定
(ページ 106-113)