• 検索結果がありません。

COST, INSURANCE AND FREIGHT

ドキュメント内 第 8 章最優先プロジェクトの 選定 (ページ 106-113)

V,

Unit Rate Amount FC LC Unit Rate Amount FC LC

(US$) (US$) (US$) (US$) (US$) (US$) (US$) (US$)

1 Tower ton 153 2,100 321,300 321,300 0 ton 201 2,100 422,100 422,100 0

2 Conductor km 30 6,200 186,000 186,000 0 km 60 6,200 372,000 372,000 0

3 OPGW 60mm2 km 0 6,100 0 0 0 km 0 6,100 0 0 0

4 OH G.W. km 10 1,550 15,500 15,500 0 km 10 1,550 15,500 15,500 0

5 Suspension Insulator String set 81 400 32,400 32,400 0 set 162 400 64,800 64,800 0

6 Tension Insulator String set 18 600 10,800 10,800 0 set 36 600 21,600 21,600 0

7 Accessories lot 1 6% 33,960 33,960 0 lot 1 6% 53,760 53,760 0

Subtotal 599,960 599,960 0 949,760 949,760 0

1 Survey & S. Investigation km 10 2,000 20,000 8,000 12,000 km 10 2,000 20,000 8,000 12,000

2 Access Construction km 20 1,000 20,000 6,000 14,000 km 20 1,000 20,000 6,000 14,000

3 Land Clearing km 10 1,000 10,000 2,000 8,000 km 10 1,000 10,000 2,000 8,000

4 Foundation (Volume of Concrete) m

3

210 750 157,500 31,500 126,000 m

3

227 750 170,250 34,050 136,200

5 Tower Erection ton 153 240 36,720 11,016 25,704 ton 201 240 48,240 14,472 33,768

6 Stringing km 10 3,000 30,000 9,000 21,000 km 20 3,000 60,000 18,000 42,000

7 Inland Transportion CIF*12% 71,995 0 71,995 CIF*12% 113,971 0 113,971

8 Miscellaneous lot 1 5% 17,311 3,376 13,935 lot 1 5% 22,123 4,126 17,997

9 General Expenses lot 1 10% 36,353 7,089 29,263 lot 1 10% 46,458 8,665 37,794

Subtotal 399,879 77,981 321,898 511,043 95,313 415,730

Total 999,839 677,941 321,898 1,460,803 1,045,073 415,730

Estimated Condition ; Aluminum base LME 1550US$/ton, Exchange Rate ; 100Yen/US$, 3.0Yen/THB

表10.3-2(4) Assumpted Estimation for TL Construction Cost Vol.4

"Voltage; 115kV, Conductor; Drake, Single, Soil Condition; Normal, Passing Area; Plain "

Items Remarks

Unit Q'ty Unit Q'ty

Laos ( Lao People's Democratic Republic ) for

Assumption:

(1) Length: 10km

(2) Ratio of Tenssion Towers for All Towers: 90% of Suspenssion Towers (27units), 10% of Tenssion Towers (3units) (3) Average Span: 350m

(4) Foundation Type: 100% of Pad Type Foundations (5) Soil Conditions: Normal

115kV, 1cct, (10km) Condutcor : Drake, Single

115kV, 2cct, (10km) Condutcor : Drake, Single

COSTOF LABOUR, INLAND TRANSPORTATION AND EXPENSES

Cat e gor y No.

COST, INSURANCE AND FREIGHT

Unit Rate Amount FC LC Unit Rate Amount FC LC

(US$) (US$) (US$) (US$) (US$) (US$) (US$) (US$)

1 Tower ton 251 2,100 527,100 527,100 0 ton 361 2,100 758,100 758,100 0

2 Conductor km 60 8,400 504,000 504,000 0 km 120 8,400 1,008,000 1,008,000 0

3 OPGW 60mm2 km 10 6,100 61,000 61,000 0 km 10 6,100 61,000 61,000 0

4 OH G.W. km 10 1,550 15,500 15,500 0 km 10 1,550 15,500 15,500 0

5 Suspension Insulator String set 162 600 97,200 97,200 0 set 162 800 129,600 129,600 0

6 Tension Insulator String set 36 800 28,800 28,800 0 set 36 1,000 36,000 36,000 0

7 Accessories lot 1 6% 70,356 70,356 0 lot 1 6% 116,832 116,832 0

Subtotal 1,303,956 1,303,956 0 2,125,032 2,125,032 0

1 Survey & S. Investigation km 10 2,000 20,000 8,000 12,000 km 10 2,000 20,000 8,000 12,000

2 Access Construction km 20 1,000 20,000 6,000 14,000 km 20 1,000 20,000 6,000 14,000

3 Land Clearing km 10 1,000 10,000 2,000 8,000 km 10 1,000 10,000 2,000 8,000

4 Foundation (Volume of Concrete) m

3

372 750 279,000 55,800 223,200 m

3

429 750 321,750 64,350 257,400

5 Tower Erection ton 251 240 60,240 18,072 42,168 ton 361 240 86,640 25,992 60,648

6 Stringing km 20 3,000 60,000 18,000 42,000 km 30 3,000 90,000 27,000 63,000

7 Inland Transportion CIF*12% 156,475 0 156,475 CIF*12% 255,004 0 255,004

8 Miscellaneous lot 1 5% 30,286 5,394 24,892 lot 1 5% 40,170 6,667 33,503

9 General Expenses lot 1 10% 63,600 11,327 52,273 lot 1 10% 84,356 14,001 70,355

Subtotal 699,601 124,592 575,008 927,920 154,010 773,910

Total 2,003,557 1,428,548 575,008 3,052,952 2,279,042 773,910

Estimated Condition ; Aluminum base LME 1550US$/ton, Exchange Rate ; 100Yen/US$, 3.0Yen/THB 230kV, 2cct, (10km)

Condutcor : Bittern, Single

230kV, 2cct, (10km) Condutcor : Bittern, Double

COSTOF LABOUR, INLAND TRANSPORTATION AND EXPENSES

Cat e go ry No.

COST, INSURANCE AND FREIGHT

表10.3-2(5) Assumpted Estimation for TL Construction Cost Vol.5

"Voltage; 115kV, Conductor; Drake, Single, Soil Condition; Normal, Passing Area; Plain "

Items Remarks

Unit Q'ty Unit Q'ty

Laos ( Lao People's Democratic Republic ) for

Assumption:

(1) Length: 10km

(2) Ratio of Tenssion Towers for All Towers: 90% of Suspenssion Towers (27units), 10% of Tenssion Towers (3units) (3) Average Span: 350m

(4) Foundation Type: 100% of Pad Type Foundations

(5) Soil Conditions: Normal

Unit Rate Amount FC LC Unit Rate Amount FC LC

(US$) (US$) (US$) (US$) (US$) (US$) (US$) (US$)

1 Tower ton 128 2,100 268,800 268,800 0 ton 156 2,100 327,600 327,600 0

2 Conductor km 30 4,900 147,000 147,000 0 km 60 4,900 294,000 294,000 0

3 OPGW 60mm2 km 0 6,100 0 0 0 km 0 6,100 0 0 0

4 OH G.W. km 10 1,550 15,500 15,500 0 km 10 1,550 15,500 15,500 0

5 Suspension Insulator String set 63 400 25,200 25,200 0 set 126 400 50,400 50,400 0

6 Tension Insulator String set 54 600 32,400 32,400 0 set 108 600 64,800 64,800 0

7 Accessories lot 1 6% 29,334 29,334 0 lot 1 6% 45,138 45,138 0

Subtotal 518,234 518,234 0 797,438 797,438 0

1 Survey & S. Investigation km 10 2,000 20,000 8,000 12,000 km 10 2,000 20,000 8,000 12,000

2 Access Construction km 20 1,500 30,000 9,000 21,000 km 20 1,500 30,000 9,000 21,000

3 Land Clearing km 10 1,300 13,000 2,600 10,400 km 10 1,300 13,000 2,600 10,400

4 Foundation (Volume of Concrete) m

3

147 1,100 161,700 32,340 129,360 m

3

262 1,100 288,200 57,640 230,560

5 Tower Erection ton 128 360 46,080 13,824 32,256 ton 156 360 56,160 16,848 39,312

6 Stringing km 10 4,500 45,000 13,500 31,500 km 20 4,500 90,000 27,000 63,000

7 Inland Transportion CIF*12% 62,188 0 62,188 CIF*12% 95,693 0 95,693

8 Miscellaneous lot 1 5% 18,898 3,963 14,935 lot 1 5% 29,653 6,054 23,598

9 General Expenses lot 1 10% 39,687 8,323 31,364 lot 1 10% 62,271 12,714 49,556

Subtotal 436,553 91,550 345,003 684,976 139,857 545,119

Total 954,787 609,784 345,003 1,482,414 937,295 545,119

Estimated Condition ; Aluminum base LME 1550US$/ton, Exchange Rate ; 100Yen/US$, 3.0Yen/THB

表10.3-2(6) Assumpted Estimation for TL Construction Cost Vol.6

"Voltage; 115kV, Conductor; Hawk, Single, Soil Condition; Normal, Passing Area; Mountain "

Items Remarks

Unit Q'ty Unit Q'ty

Laos ( Lao People's Democratic Republic ) for

Assumption:

(1) Length: 10km

(2) Ratio of Tenssion Towers for All Towers: 70% of Suspenssion Towers (21units), 30% of Tenssion Towers (9units) (3) Average Span: 350m

(4) Foundation Type: 100% of Pad Type Foundations (5) Soil Conditions: Normal

115kV, 2cct, (10km) Condutcor : Hawk, Single 115kV, 1cct, (10km)

Condutcor : Hawk, Single

COSTOF LABOUR, INLAND TRANSPORTATION AND EXPENSES

Cat e gor y No.

COST, INSURANCE AND FREIGHT

Unit Rate Amount FC LC Unit Rate Amount FC LC

(US$) (US$) (US$) (US$) (US$) (US$) (US$) (US$)

1 Tower ton 159 2,100 333,900 333,900 0 ton 205 2,100 430,500 430,500 0

2 Conductor km 30 6,200 186,000 186,000 0 km 60 6,200 372,000 372,000 0

3 OPGW 60mm2 km 0 6,100 0 0 0 km 0 6,100 0 0 0

4 OH G.W. km 10 1,550 15,500 15,500 0 km 10 1,550 15,500 15,500 0

5 Suspension Insulator String set 63 400 25,200 25,200 0 set 126 400 50,400 50,400 0

6 Tension Insulator String set 54 600 32,400 32,400 0 set 108 600 64,800 64,800 0

7 Accessories lot 1 6% 35,580 35,580 0 lot 1 6% 55,992 55,992 0

Subtotal 628,580 628,580 0 989,192 989,192 0

1 Survey & S. Investigation km 10 2,000 20,000 8,000 12,000 km 10 2,000 20,000 8,000 12,000

2 Access Construction km 20 1,500 30,000 9,000 21,000 km 20 1,500 30,000 9,000 21,000

3 Land Clearing km 10 1,300 13,000 2,600 10,400 km 10 1,300 13,000 2,600 10,400

4 Foundation (Volume of Concrete) m

3

210 1,100 231,000 46,200 184,800 m

3

262 1,100 288,200 57,640 230,560

5 Tower Erection ton 159 360 57,240 17,172 40,068 ton 205 360 73,800 22,140 51,660

6 Stringing km 10 4,500 45,000 13,500 31,500 km 20 4,500 90,000 27,000 63,000

7 Inland Transportion CIF*12% 75,430 0 75,430 CIF*12% 118,703 0 118,703

8 Miscellaneous lot 1 5% 23,583 4,824 18,760 lot 1 5% 31,685 6,319 25,366

9 General Expenses lot 1 10% 49,525 10,130 39,396 lot 1 10% 66,539 13,270 53,269

Subtotal 544,778 111,425 433,353 731,927 145,969 585,958

Total 1,173,358 740,005 433,353 1,721,119 1,135,161 585,958

Estimated Condition ; Aluminum base LME 1550US$/ton, Exchange Rate ; 100Yen/US$, 3.0Yen/THB 115kV, 1cct, (10km)

Condutcor : Drake, Single

115kV, 2cct, (10km) Condutcor : Drake, Single

COSTOF LABOUR, INLAND TRANSPORTATION AND EXPENSES

Cat e gor y No.

COST, INSURANCE AND FREIGHT

表10.3-2(7) Assumpted Estimation for TL Construction Cost Vol.7

"Voltage; 115kV, Conductor; Drake, Single, Soil Condition; Normal, Passing Area; Mountain "

Items Remarks

Unit Q'ty Unit Q'ty

Laos ( Lao People's Democratic Republic ) for

Assumption:

(1) Length: 10km

(2) Ratio of Tenssion Towers for All Towers: 70% of Suspenssion Towers (21units), 30% of Tenssion Towers (9units) (3) Average Span: 350m

(4) Foundation Type: 100% of Pad Type Foundations

(5) Soil Conditions: Normal

Unit Rate Amount FC LC Unit Rate Amount FC LC

(US$) (US$) (US$) (US$) (US$) (US$) (US$) (US$)

1 Tower ton 259 2,100 543,900 543,900 0 ton 369 2,100 774,900 774,900 0

2 Conductor km 60 8,400 504,000 504,000 0 km 120 8,400 1,008,000 1,008,000 0

3 OPGW 60mm2 km 10 6,100 61,000 61,000 0 km 10 6,100 61,000 61,000 0

4 OH G.W. km 10 1,550 15,500 15,500 0 km 10 1,550 15,500 15,500 0

5 Suspension Insulator String set 126 600 75,600 75,600 0 set 126 800 100,800 100,800 0

6 Tension Insulator String set 108 800 86,400 86,400 0 set 108 1,000 108,000 108,000 0

7 Accessories lot 1 6% 73,524 73,524 0 lot 1 6% 120,432 120,432 0

Subtotal 1,359,924 1,359,924 0 2,188,632 2,188,632 0

1 Survey & S. Investigation km 10 2,000 20,000 8,000 12,000 km 10 2,000 20,000 8,000 12,000

2 Access Construction km 20 1,500 30,000 9,000 21,000 km 20 1,500 30,000 9,000 21,000

3 Land Clearing km 10 1,300 13,000 2,600 10,400 km 10 1,300 13,000 2,600 10,400

4 Foundation (Volume of Concrete) m

3

372 1,100 409,200 81,840 327,360 m

3

543 1,100 597,300 119,460 477,840

5 Tower Erection ton 259 360 93,240 27,972 65,268 ton 369 360 132,840 39,852 92,988

6 Stringing km 20 4,500 90,000 27,000 63,000 km 30 4,500 135,000 40,500 94,500

7 Inland Transportion CIF*12% 163,191 0 163,191 CIF*12% 262,636 0 262,636

8 Miscellaneous lot 1 5% 40,932 7,821 33,111 lot 1 5% 59,539 10,971 48,568

9 General Expenses lot 1 10% 85,956 16,423 69,533 lot 1 10% 125,031 23,038 101,993

Subtotal 945,519 180,656 764,863 1,375,346 253,421 1,121,925

Total 2,305,443 1,540,580 764,863 3,563,978 2,442,053 1,121,925

Estimated Condition ; Aluminum base LME 1550US$/ton, Exchange Rate ; 100Yen/US$, 3.0Yen/THB

表10.3-2(8) Assumpted Estimation for TL Construction Cost Vol.8

"Voltage; 115kV, Conductor; Drake, Single, Soil Condition; Normal, Passing Area; Plain "

Items Remarks

Unit Q'ty Unit Q'ty

Laos ( Lao People's Democratic Republic ) for

Assumption:

(1) Length: 10km

(2) Ratio of Tenssion Towers for All Towers: 70% of Suspenssion Towers (21units), 30% of Tenssion Towers (9units) (3) Average Span: 350m

(4) Foundation Type: 100% of Pad Type Foundations (5) Soil Conditions: Normal

230kV, 2cct, (10km) Condutcor : Bittern, Single

230kV, 2cct, (10km) Condutcor : Bittern, Double

COSTOF LABOUR, INLAND TRANSPORTATION AND EXPENSES

Ca te go ry No.

COST, INSURANCE AND FREIGHT

表10.3-5 2010-2030年の送電線開発計画

(unit: 1,000USD) origination terminal voltage (kV) year No. of cct conductor type length (km) area UXO pollution total 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 Northern

Boun Neua Namo 115 2012 2 ACSR240 96.0 Mountain N/A 14,231 FC 8,998.0 990 6,748 1,260

2012 LC 5,233.2 628 3,035 1,570

Boun Neua Cu Mining 115 2012 1 ACSR240 65.0 Mountain N/A 6,206 FC 3,963.6 436 2,973 555

2012 LC 2,242.5 269 1,301 673

Boun Neua Cu Mining 115 2014 1 ACSR240 65.0 Mountain N/A 6,206 FC 3,963.6 436 2,973 555

2014 LC 2,242.5 269 1,301 673

Luang Namtha Cu Mining 115 2010 1 ACSR240 60.0 Mountain N/A 5,729 FC 3,658.7 3,659

2010 LC 2,070.0 2,070

Namo Cu Mining 115 2012 1 ACSR240 15.0 Mountain N/A 1,432 FC 914.7 101 686 128

2012 LC 517.5 62 300 155

Nam Ou 6 Boun Neua 115 2017 2 ACSR240 40.0 Mountain N/A 5,930 FC 3,749.2 412 2,812 525

2017 LC 2,180.5 262 1,265 654

Luang Namtha Nam Thoung 115 2012 2 ACSR240 91.0 Mountain N/A 13,490 FC 8,529.3 938 6,397 1,194

2012 LC 4,960.6 595 2,877 1,488

Luang Namtha Namo 115 2015 1* ACSR240 42.7 Mountain N/A 1,276 FC 992.6 993

2015 LC 283.7 284

Nam Thoung Houayxai 115 2012 1 ACSR240 40.0 Mountain N/A 3,819 FC 2,439.1 268 1,829 341

2012 LC 1,380.0 166 800 414

Nam Thoung Nam Tha 1 115 2012 2 ACSR240 42.0 Mountain N/A 6,226 FC 3,936.6 433 2,952 551

2012 LC 2,289.5 275 1,328 687

Nam Tha 1 Hongsa 115 2015 2 ACSR410 93.0 Mountain N/A 16,006 FC 10,557.0 1,161 7,918 1,478

2015 LC 5,449.4 654 3,161 1,635

Nam Beng Switching Station 115 2020 1 ACSR240 15.0 Mountain N/A 1,432 FC 914.7 101 686 128

2020 LC 517.5 62 300 155

Oudomxai Namo 115 2013 1* ACSR240 41.0 Mountain N/A 1,226 FC 953.1 953

2013 LC 272.4 272

Luangprabang 2 Oudomxai 115 2013 1* ACSR240 51.8 Mountain N/A 1,548 FC 1,204.2 1,204

2013 LC 344.2 344

Oudomxai THLC Mining 115 2012 1 ACSR240 20.0 Mountain N/A 1,910 FC 1,219.6 134 915 171

2012 LC 690.0 83 400 207

Luangprabang 2 Cement Factory 115 2010 1 ACSR240 25.0 Mountain Light 2,387 FC 1,524.5 1,524

2010 LC 862.5 863

2010 300 FC 99.0 99

2010 LC 201.0 201

Luangprabang 2 United 115 2010 1 ACSR240 15.0 Mountain Light 1,432 FC 914.7 915

2010 LC 517.5 518

2010 180 FC 59.4 59

2010 LC 120.6 121

Nam Nga Luangprabang 2 115 2020 1 ACSR240 15.0 Mountain N/A 1,432 FC 914.7 101 686 128

2020 LC 517.5 62 300 155

Luangprabang 1 Luangprabang 2 115 2013 1* ACSR240 86.9 Mountain Light 2,598 FC 2,020.2 222 1,515 283

2013 LC 577.4 69 335 173

2013 1,043 FC 344.1 310 34

2013 LC 698.7 629 70

Luangprabang 1 Luangprabang 3 115 2013 2 ACSR240 15.0 Mountain N/A 2,224 FC 1,405.9 155 1,054 197

2013 LC 817.7 98 474 245

Hongsa Luangprabang 3 115 2015 2 ACSR410 100.0 Mountain N/A 17,211 FC 11,351.6 1,249 8,514 1,589

2015 LC 5,859.6 703 3,399 1,758

Mekong Luangprabang Luangprabang 3 115 2016 2 ACSR410 40.0 Mountain Light 6,884 FC 4,540.6 499 3,405 636

2016 LC 2,343.8 281 1,359 703

2016 480 FC 158.4 143 16

2016 LC 321.6 289 32

Nam Ma 1 Nam Ma 2 115 2016 1 ACSR240 20.0 Mountain Light 1,910 FC 1,219.6 134 915 171

2016 LC 690.0 83 400 207

2016 240 FC 79.2 71 8

2016 LC 160.8 145 16

Nam Ma 2 Nam Ma 3 115 2016 1 ACSR240 20.0 Mountain Light 1,910 FC 1,219.6 134 915 171

2016 LC 690.0 83 400 207

2016 240 FC 79.2 71 8

2016 LC 160.8 145 16

Nam Ma 1 Xam Neua 115 2016 2 ACSR240 40.0 Mountain Heavy 5,930 FC 3,749.2 412 2,812 525

2016 LC 2,180.5 262 1,265 654

2016 680 FC 224.4 202 22

2016 LC 455.6 410 46

Xam Neua Muong Kham 115 2011 2 ACSR240 146.0 Mountain Heavy 21,643 FC 13,684.4 11,769 1,916

2011 LC 7,958.8 5,571 2,388

表10.3-5 2010-2030年の送電線開発計画

(unit: 1,000USD) origination terminal voltage (kV) year No. of cct conductor type length (km) area UXO pollution total 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030

2011 2,482 FC 819.1 737 82

2011 LC 1,662.9 1,497 166

Nam Khan 2 Nam Khan 3 115 2018 1 ACSR240 45.0 Mountain Light 4,297 FC 2,744.0 302 2,058 384

2018 LC 1,552.5 186 900 466

2018 540 FC 178.2 160 18

2018 LC 361.8 326 36

Luangprabang 3 Nam Khan 2 230 2018 2 ACSR610 36.0 Mountain N/A 8,300 FC 5,546.1 610 4,160 776

2018 LC 2,753.5 330 1,597 826

Nam Mo 1 Muong Kham 115 2020 1 ACSR240 45.0 Mountain Heavy 4,297 FC 2,744.0 302 2,058 384

2020 LC 1,552.5 186 900 466

2020 765 FC 252.5 227 25

2020 LC 512.6 461 51

Muong Kham Fe Mining 115 2011 1 ACSR240 40.0 Mountain Heavy 3,819 FC 2,439.1 2,098 341

2011 LC 1,380.0 966 414

2011 680 FC 224.4 202 22

2011 LC 455.6 410 46

Phonsavan Muong Kham 115 2011 2 ACSR410 56.2 Mountain Heavy 9,673 FC 6,379.6 5,486 893

2011 LC 3,293.1 2,305 988

2011 955 FC 315.3 284 32

2011 LC 640.1 576 64

Phonsavan Fe Mining 115 2012 1 ACSR240 20.0 Mountain Heavy 1,910 FC 1,219.6 134 915 171

2012 LC 690.0 83 400 207

2012 340 FC 112.2 101 11

2012 LC 227.8 205 23

Xayabury Paklay 115 2014 2 ACSR240 134.0 Plain N/A 16,392 FC 11,318.0 1,245 8,489 1,585

2014 LC 5,073.8 609 2,943 1,522

Paklay Cu Mining 115 2014 1 ACSR240 25.0 Mountain N/A 2,387 FC 1,524.5 168 1,143 213

2014 LC 862.5 104 500 259

Paklay Thali 115 2014 1 ACSR240 86.2 Plain N/A 6,963 FC 4,785.8 526 3,589 670

2014 LC 2,177.2 261 1,263 653

New Switching Station (TNam San 3 115 2016 1 ACSR240 28.0 Mountain Light 2,673 FC 1,707.4 188 1,281 239

2016 LC 966.0 116 560 290

2016 336 FC 110.9 100 11

2016 LC 225.1 203 23

Namo Cement Factory 115 2012 1 ACSR240 5.0 Mountain N/A 477 FC 304.9 34 229 43

2012 LC 172.5 21 100 52

TL Construction Northern Total

213,416

FC

139,254.00

28,885 26,942 9,349 21,470 20,865 13,800 5,466 6,743 1,664 3,430 640 0 0 0 0 0 0 0 0 0 0

LC

74,162.00

14,454 14,398 7,474 8,498 10,544 7,923 3,842 3,151 1,602 1,500 776 0 0 0 0 0 0 0 0 0 0

UXO Removal Northern Total

9,262

FC

3,055.00

1,482 446 11 34 587 0 225 0 245 0 25 0 0 0 0 0 0 0 0 0 0

LC

6,207.00

3,010 905 23 70 1,192 0 459 0 497 0 51 0 0 0 0 0 0 0 0 0 0

ドキュメント内 第 8 章最優先プロジェクトの 選定 (ページ 106-113)

関連したドキュメント