• 検索結果がありません。

1. Objective of waterproofing building connections by freezing 3. Freezing operation status and tasks

N/A
N/A
Protected

Academic year: 2022

シェア "1. Objective of waterproofing building connections by freezing 3. Freezing operation status and tasks"

Copied!
1
0
0

読み込み中.... (全文を見る)

全文

(1)

Status of and measures for removing highly contaminated water in trench

1. Objective of waterproofing building connections by freezing 3. Freezing operation status and tasks

4. Countermeasures and future plans

 When removing contaminated water which remains inside the seawater pipe trench at the seaward side of Units 2 and 3’s turbine buildings, we waterproof the building connections by freezing them. Once this is completed, we will remove the stagnant water and block the inside of the trench.

2. Difference between freezing environment in trench and ice wall

 We began the freezing operation on April 28th, but it takes time for the temperature to fall at places which are not filled with packers (①) and gaps at the upper side of pipes (②) etc.

 Water flow, caused by fluctuation of the water level at the turbine building, is one of the factors that inhibits freezing.

 Fluctuation of the water level in the turbine building occurs due to injection of cooling water into the reactor, inflow of groundwater and water transfer between buildings to keep the water level lower than the groundwater around the building.

立坑A

Bird’s-eye view of Unit 2 seawater pipe trench

2号機タービン建屋

A

Ice wall Inside trench

No

Large (from the effects of disturbance and convection)

Large (per unit volume) Small (per unit volume) Water

quantity Water freezing

status (illustration)

Yes (civil engineering work etc.) Small

Water flow

Previous experience

Water in gaps Soil grain

Water only

 Because of the large water quantity and water flow inside the trench, it is more difficult to freeze water than in soil conditions.

 Creating similar conditions to soil by installing packers (nylon bags) inside the trench and inserting cement makes it easier to freeze

the water. Packers (conceptual

diagram)

Packers (during trial run)

Cable Tray

Duct

Duct Packers

 We are taking the following measures sequentially, and monitoring the fluctuation of the water level and changes in the freezing temperature.

 Completion of freezing at Unit 2 has been postponed from the end of June to the middle of July (Unit 3’s schedule remains unchanged.)

 ①Replacing the sight tubes with freezing ducts to improve the freezing capacity, starting operation from June 4th.

 ②We plan to install more freezing ducts outside the frame to improve the freezing capacity.

 ③Regulating the amount of water transfer from the turbine building from June 10th to reduce water flow.

 ④We plan to inject grout between the turbine building and packers to reduce water flow.

Unit 2 turbine building

Replace the sight tubes with freezing ducts

Install more freezing ducts outside the frame

Inject grout Install more freezing ducts outside the frame

Top View

Assumed frozen soil area

Assumed frozen soil area

Packers (only

at lower part) Packers (whole)

Areas frozen

approx 6,000 approx

5,000 Contamin- ated water

quantity inside trench (m3)

Radioactivity Concentration Cs137 (Bq/cm3)

Trench

approx 104 approx

104 Turbine Building approx

104 Unit 2

approx 102 Unit 3

参照

関連したドキュメント

Knowing from the Motzkin Straus theorem 27 or see, e.g., 26 that maxx Ax/K 2 1 − 1/K holds exactly if there is a maximum clique with size K indicated by a binary vector x, we see

We show that some boundary value problems governed by a second order or- dinary differential equation admits solutions with slope in a known pre-specified region of the positive

SAS ∗ with some invertible bounded linear or conjugate-linear operator S on H pre- serves Lebesgue decompositions in both directions, we see that the transformation in (2.5) is

I have since perceived, that whatever form be adopted, to represent the Linear Symbol of Quaternion Operation thus referred to, that symbol always satisfies a certain

It follows by Theorem 5.1 and Corollary 5.3 that X is a metric Euclidean building and that it factors as a product of irreducible Euclidean buildings, cones on spherical

The repeated homogeneous balance method is used to construct new exact traveling wave solutions of the (2+1) dimensional Zakharov- Kuznetsov (ZK) equation, in which the

In this paper we give two existence theorems for a class of elliptic problems in an Orlicz-Sobolev space setting concerning both the sublinear and the superlinear case with

Moreover, at about the same time, a few other constructions of such linear Sode -connections were published independently by Massa and Pagani [7] and by Byrnes [3], and these are