Regarding the stoppage of the water pump transfer from the "K" 

Download (0)

Full text

(1)

Summary:

Regular patrol found that the pump transferring water from the "K" Drainage to the "C" Drainage had stopped. The earth  leakage circuit breaker of the generator was in operation and the electrical source was down. As a result, water from the 

"K" Drainage was not being diverted to the port and was flowing out to the ocean.

Time and Date of the Incident:

Tuesday, 21 April 2015, problem identified at approximately 8:45 Measures taken since the start of the operation:

Start of operation: Friday, 17 April from 13:33 Three operations a day  since the start, at 8:00. 12:00 and 14:30 daily.

20 April 14:30, patrol finds no abnormalities found neither in the  transfer pump or the generator.

21 April 8:45, patrol finds that transfer pump has stopped.

Today's survey result:

Attempts were made at the site to restore the earth leakage circuit  breaker via the generator and insulation resistance measurement was 

taken on the control panel and the pump. Neither showed any irregularities so it was decided that the generator was  causing the stoppage.

The generator engine interior as well as the control panel was checked for rainwater and other substance, but none was  found. The generator will be brought off site and checked internally.

*As of 8:09 PM on 21 April, the generator was replaced with an emergency generator and pumping and water transfer  were re‐started. 

Regarding the stoppage of the water pump transfer from the "K" 

Drainage to the "C" Drainage at Fukushima Daiichi

Generator Control 

panel

Transferring pumps

<Reference>

April 21 2015 Tokyo Electric Power Company

1

(2)

Overview of “K” Drainage water discharging pump installation plan (Ahead of rerouting “K” Drainage to discharge inside the port, “K” 

Drainage rainwater has been transferred to “C” Drainage (which leads to the port) using the pumps installed as below. (operation started   April 17 13:33.)

Drainage K

“C” Drainage

Transfer line Distance: 80m A

(Seaside)

(Plan) A

“C” Drainage

(Seaside)

8 temporary pumps

(Mountain Side)

Bottom plate Transferring line

Groundwater bypass line

Detail

Groundwater bypass line “C” Drainage  (Catch basin) Photo

Horizontal pipe (Photo①)

Pumps (Photo) Photo

A‐A Section A

Generator

“C” Drainage

[Pump specification]

2 6‐inch pumps

Capacity/pump: 0.055m3/sec

6 8‐inch pumps

Capacity/pump: 0.075m3/sec

Total capacity

6‐inch pumps: 0.055m3/sec×20.11m3/sec 8‐inch pumps: 0.075m3/sec×6=0.45m3/sec

Total capacity: 0.56m3/sec (Approx. 2000m3/h)

2 North

Regarding the stoppage of the water pump transfer from the "K" 

Drainage to the "C" Drainage at Fukushima Daiichi

South embankment

Temporary dyke

Groundwater  bypass line Temporary dyke

8 temporary  pumps

Transferring line

(3)

3

<Reference> Drainage control inside the port  (Plan for rerouting “K” Drainage)

Note: the above figure is extracted from the materials for the April 13, 2015 “On‐site adjustment meeting for decommissioning/decontamination water countermeasures

Drainage control is to be performed inside the port by rerouting “K” Drainage into the port within  FY2015. (piping route is under examination)

Exit of “K” Drainage is  to be joined with the  exits of existing “B” 

and “C” Drainage

New route for “K” Drainage

New route for “B” & “C” 

Drainages (completed) Existing “K” Drainage route

(4)

4

<Reference> Drainage layout

Area

“A” Drainage

“A” Drainage

“C” Drainage

“K” Drainage

“K” Drainage

“B” Drainage

“C” Drainage Unit 1 Unit 2 Unit 3 Unit 4

The same point  with C‐2‐1

Side gutter drainage  radiation monitor Loading dock 

drainage

Unit 6 Unit 5

: Major drainage, river : Side ditch, branch pipes

: Manual sampling  by TEPCO employee       (Before Jan 14, 2015)

: Automatic water sampling       (after Jan 19, 2015)

Jinbasawa River

Figure

Updating...

References

Related subjects :